For critical path A-C-G-I and minimum duration 23: axis 0–25; critical activities A, C, G, I on one line; B, D, E, F, H, J each on separate lines.
Activity D: solid bar 4–7 (duration 3), dotted bar 7–12 (float 5).
Exam questions often provide a grid and axes. Use them to draw the chart accurately.
Ensure critical activities are truly back-to-back with no gaps. Check that non-critical bars show both solid (activity) and dotted (float) parts correctly.